United Therapeutics Phase III

Mixed Use | Office | Retail

The Challenge:

A detailed schedule submission was required at the onset of the project, typical any project. However, the Whiting-Turner Company was faced with challenge of procuring the window contractor in Germany while coordinating design efforts to establish the estimated fabrication and installation time.

Our Solution:

Through various planning meetings, Whiting-Turner & Aegis ensured that all information (pull-plan, design information, detailed schedules for design & fabrication) were accounted for in the CPM schedule and revalidated on a periodic basis. Resultantly, this would then allow the site team to prioritize the planned multiple curtainwall deliveries and their respective installations. Through the use of P6, the site team conducted “what-if” schedule meeting reviews to mitigate on-going or potential issues.


See All Featured Projects

Budget:

$32 Million


Location:

Silver Spring, MD