Inova Women and Children’s Hospital

Healthcare

The Challenge:

The challenge was to install new utilities, and a new structure on a crowded campus, and deliver the project early. What’s more the electrical subcontractor went bankrupt during the start of the MEPS fit out stage.

Our Solution:

We created a detailed CPM schedule which was managed on a short term basis using a Short Interval (SIPS) schedule on a da-to-day basis.  We were able to help Clark Construction deliver the project earlier than anticipated and win E&R’s Healthcare Award of Merit, and best Healthcare Project.


See All Featured Projects

Budget:

$217 Million