The Challenge:
The site had to remain operational during construction as well as having a complex Maintenance of Plant Operations (MOPO)
Our Solution:
Aegis worked with the GC to develop a detailed schedule, that was tracked into one day tasks on occasion. Additionally, the GC and Aegis implemented a daily update plan which resulted in the project finishing a month early.